Equipment shortages add pressure to LNG plant costs, Kiewit says



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>Equipment shortages add pressure to LNG plant costs, Kiewit says</title></head><body>

New LNG plant construction costs up to 30% in five years

Higher costs reflected in tariffs charged new customers

Wages up 20%

By Curtis Williams

HOUSTON, Sept 19 (Reuters) -The boom in U.S. construction of liquefied natural gas (LNG) plants has led to shortages of generators, electric motors and transformers, contributing to higher costs and construction delays, Kiewit Energy President Tom Shelby said on Thursday.

Equipment shortages and rising costs for equipment, wages and cement have driven up the cost of constructing new LNG plants by between 25% and 30% over the last five years, Shelby said, noting that wages have increased by 20% in keeping with inflationary costs.

Kiewit, among the largest U.S. contractors, has been involved in building LNG plants including Venture Global's 12 million tons per annum (MTPA) plant at Calcasieu Pass, Louisiana.

"For most of my career transformers from order to supply took one year. Now, it's up to nearly two years," Shelby told Reuters on the sidelines of the Gastech conference in Houston.

Separately, energy researcher Wood Mackenzie said fees LNG developers charge new customers to liquefy gas have been climbing.

Twenty-year gas processing deals signed in 2022 and early 2023 were priced between $2.15 per million British thermal units and $2.30/mmBtu. More recent deals have put tariffs in the $2.40/ mmBtu to $2.50/mmBtu range, Wood Mackenzie said.

Equipment availability can no longer be taken for granted, and shortages have been compromising quality.

"It affects us as an EPC (engineering, procurement and construction) contractor in terms of the quality and the time," said Shelby.

There are five LNG plants under development in Texas and Louisiana and 16 others on the drawing board looking to secure investment and customers. The five under construction would add a combined 86.6 million metric tons per annum (MTPA) of the superchilled gas.

Work at Golden Pass LNG, one of the largest U.S. projects, largely halted after its main contractor ran $2.4 billion over the original budget and filed for bankruptcy earlier this year. The project's joint owners, QatarEnergy QATPE.UL and Exxon Mobil XOM.N, recently asked for a three year extension to their construction permit.



Reporting by Curtis Williams in Houston; Editing by David Gregorio

</body></html>

Disclaimer: The XM Group entities provide execution-only service and access to our Online Trading Facility, permitting a person to view and/or use the content available on or via the website, is not intended to change or expand on this, nor does it change or expand on this. Such access and use are always subject to: (i) Terms and Conditions; (ii) Risk Warnings; and (iii) Full Disclaimer. Such content is therefore provided as no more than general information. Particularly, please be aware that the contents of our Online Trading Facility are neither a solicitation, nor an offer to enter any transactions on the financial markets. Trading on any financial market involves a significant level of risk to your capital.

All material published on our Online Trading Facility is intended for educational/informational purposes only, and does not contain – nor should it be considered as containing – financial, investment tax or trading advice and recommendations; or a record of our trading prices; or an offer of, or solicitation for, a transaction in any financial instruments; or unsolicited financial promotions to you.

Any third-party content, as well as content prepared by XM, such as: opinions, news, research, analyses, prices and other information or links to third-party sites contained on this website are provided on an “as-is” basis, as general market commentary, and do not constitute investment advice. To the extent that any content is construed as investment research, you must note and accept that the content was not intended to and has not been prepared in accordance with legal requirements designed to promote the independence of investment research and as such, it would be considered as marketing communication under the relevant laws and regulations. Please ensure that you have read and understood our Notification on Non-Independent Investment. Research and Risk Warning concerning the foregoing information, which can be accessed here.

Risk Warning: Your capital is at risk. Leveraged products may not be suitable for everyone. Please consider our Risk Disclosure.